What is being built
The projects moving the market
A second urban core is forming on the East Bank, 550 acres between the Cumberland River and Interstates 24 and 65, about 130 of them owned by Metro.[26] The East Bank Development Authority keeps the district map and schedule. Downtown, the Gulch and the airport keep building.
- 01
Oracle campus, East Bank
A $4.5 billion campus planned at about 1.3 million square feet of office across 23 buildings on roughly 82 acres, with 8,500 jobs targeted by 2031. Groundbreaking is planned for November 2026. Incentives include a $65 million state grant and up to $175 million in Metro property tax abatements. Metro notes Oracle has reduced its planned office footprint.[14][15]
- 02
New Nissan Stadium
About $2.2 billion, 75 percent complete at the end of March 2026, opening February 2027 with the first Titans season that fall. With Eastpoint Flats, the first East Bank project after Metro signed development documents in March 2026, it is pulling hotel, multifamily and infrastructure investment across the river.[17][16][2]
- 03
East Bank infrastructure
Metro has allocated $300 million, with estimates of $285 to $355 million across James Robertson Parkway, the Marine Drive and Cowan extension, utilities, and parks. East Bank Boulevard is still in right-of-way acquisition and is now phased.[15]
- 04
The East Bend, East Bank
A local investor group bought the 47-acre former PSC Metals scrapyard just south of Nissan Stadium in August 2025 and plans a mixed-use, family-oriented riverfront neighborhood of homes, parks and greenways. Metro Planning Commission and Metro Council approved the rezoning unanimously in 2026, and the Planning Commission approved its Major and Collector Streets Plan on September 24, 2026. Gensler leads architecture and planning with OJB on landscape. A public realm master plan for its parks and streets is next. The Nashville Business Journal named the site purchase its 2026 Real Estate Deal of the Year.[27]
- 05
Downtown and the Gulch
Nashville Yards is now a working mixed-use district, and developers have filed for another office tower. Starbucks leased all 250,000 square feet of office at Peabody Union for a hub of up to 2,000 jobs. The Nashville EDITION broke ground in the Gulch: 28 stories, 261 rooms and 84 residences, opening 2028.[2][19][20]
- 06
BNA airport